KOREA-CTV building progress in FEB, 2025
Page Information
Author manager
Views 66 Date Posted March 6, 2025 17:45 PM
Views 66 Date Posted March 6, 2025 17:45 PM
Content
The 27-meter-class KOREA-CTV, currently under construction in South Korea using state-of-the-art shipbuilding technology with class BV, held its Keel Laying Ceremony at the shipyard on December 10, 2024.
As of the end of February, the assembly process for the Engine Room Block and Tank Room Block is underway.
The KOREA-CTV is being built with four Volvo IPS engines and a Dynamic Positioning System (DPS), enabling it to transport offshore personnel and equipment at a speed of 25 knots within offshore wind farm areas. The vessel is scheduled for delivery on June 30, 2025.